Aurizona Construction Photos

August 2017

Early works construction commenced in August, focused on dismantling unnecessary buildings from the existing processing plant. To explore the gallery, click on an image or video.

September 2017

September activities focused on plant refurbishment, and staging equipment and supplies for the tailings facility raise. To explore the gallery, click on an image or video.

October 2017

October saw significant groundworks activity as the team prepared the area for the grinding circuit and the pre-leach thickeners, and continued with the tailings facility raise. There were also three rigs drilling below and to the west of the Piaba pit to confirm the extension of mineralization at depth and along strike. To explore the gallery, click on an image or video.

November 2017

Work in November continues to focus on plant refurbishment and the tailings dam raise, with additional groundwork to prepare for installation of the crushing circuit and the incinerator. To explore the gallery, click on an image or video.